216 Ridgedale Rd

Mon 20 October, 2003

First-floor framing resumes. The library and bathroom walls are in place, as it the refrigerator nook. After several tries, the kitchen windows are properly framed. The mechanical closet remains, as well as several modifications upstairs along with a proper sizing of the rough opening for the back door.

The pictures below are from the morning visit, before the new framing began.

Plastic to help keep rain out
Front yard raked . . .
. . . And the inside swept
Kitchen framing
Living room
Main breaker panel
Absent east window
"4-ganger" in the M bath
Upstairs sweepings
Sorted rubble
Backyard raked
Free parking
     


Prev Main Next