216 Ridgedale Rd

Sun 26 October, 2003

Ductwork for heating was delivered late Friday evening; temporarily stored in first-floor bathroom.

Sunday afternoon, take care of several loose ends such as finishing runs of network cable and installing junction boxes, adding headers for closet light fixtures, and cleaning up the work site.

Heating ducts delivered
Network junction boxes
MBR closet light fixture
Brace for laundry closet light
 