216 Ridgedale Rd
Sun 30 November, 2003
Review of work completed last Wed and Fri.
Cedar siding installed on east side and across most of front of the house.
Kitchen tile laid and grouted.
Tile in half-bath on first floor laid and sealed.
Tile in second bath upstairs laid and grouted.
Water heater installed and water lines connected. Gas connections, vent yet to be done.
Drywall finishing finally complete.
Siding works its way across the front of the house
Row upon row of cedar
East side complete
Final caulking of seams and holes
Kitchen tile, grouted
Kitchen from dining room
Half-bath tile, sealed (still wet)
Far corner of half-bath
Water heater installed
A snug fit
Water main fully connected at last
Vent for water heater not yet connected
Tile in second bathroom, grouted
Entrance to second bathroom
Few leftovers from the tile-laying
Cutout for shower to be installed in master bath