216 Ridgedale Rd

Daily Sequence

The front of the house each day during construction.

Thu May 15, 2003: House inspection
Wed Oct 01, 2003: Construction begins
Thu Oct 02, 2003: Roof is gone
Fri Oct 03, 2003: Framing begins
Mon Oct 06, 2003: Three of four walls framed and in place
Tue Oct 07, 2003: New roof is on
Wed Oct 08, 2003: Interior framing of second story complete
Thu Oct 09, 2003: Ice-water barrier in place on roof
Wed Oct 15, 2003: Doors removed, First floor framing in progress
Mon Oct 20, 2003: Additional plastic over roof, yard raked, inside cleaned
Tue Oct 21, 2003: All but two second-story windows installed, most rough openings below cut out
Wed Oct 22, 2003: Upstairs wiring complete, some more front siding removed
Tue Oct 28, 2003: Framing for fist-floor windows and doorways finally finished
Wed Oct 29, 2003: Exterior walls prepped for siding, most first-floor windows in
Fri Oct 31, 2003: More plumbing progress, heating work begins in earnest
Sun Nov 02, 2003: Soffit, fascia, trim completed Friday afternoon
Mon Nov 03, 2003: Roof work begun on Friday is visible
Tue Nov 04, 2003: Heating work; more roofing; LR triple window installed
Wed Nov 05, 2003: Roofing complete; Drain and vent line rough-in finished; more heating progress; electrical connection imminent
Fri Nov 07, 2003: Front and rear entry doors installed; all Hardi-panel siding up; hot/cold plumbinbg rough-in underway
Mon Nov 17, 2003: Extensive drywall, gas, heating, plumbing progress inside. Remaining windows covered with plastic sheeting.
Mon Nov 24, 2003: Triple window in MBR, cedar beltway border between Hardi-panel and cedar, flashing installed
Sun Nov 30, 2003: Cedar siding begins to go up.
Tue Dec 02, 2003: Siding complete (almost). Real snow falls.